Waste-to-Energy Plants in Spain
La Coruna
Location: A Coruna
Operator: SOGAMA - Soc Galega do Medio Ambientehas
Configuration: 1 X 49 MW
Operation: 1999
Fuel: refuse
Boiler/incinerator system supplier: Kvaerner
T/G supplier: Skoda
Quick Facts: The WTE plant is the centerpiece of a large integrated waste treatment and waste disposal complex in Galicia and features a BFB boiler.

Photograph courtesy of SOGAMA
Posted 12 Apr 2002

Mataro
Location: Barcelona
Operator: Tractament i Revaloritzacio de Residus del Maresme SA (TRM)
Configuration: 1 X 11.6 MW
Operation: 1994
Fuel: refuse
Boiler/incinerator system supplier: Martin
T/G supplier: GEC-Alstom
EPC: Tiru, Sogea
Quick Facts: TRM is a joint venture of Tiru (45%), Acciona (45%), and Endesa (10%). The plant has two grate furnace lines with a design throughput of 160,000 tpy of MSW plus a sorting center that can handle 40,000 tpy, all collected in 26 municipalities of the Maresme region in northeast Catalonia. The plant was upgraded in 2002/03 and has ISO 9002 and ISO 14001 certification.

Photograph courtesy of Groupe Tiru
Posted 7 Apr 2007

Mellila Remesa
Location: Melilla
Operator: REMESA - Residuos de Melilla SA
Configuration: 1 X 2.2 MW
Operation: 1996
Fuel: refuse
Boiler/incinerator system supplier: Von Roll
T/G supplier: ??
Quick Facts: REMESA is a 50:50 JV of La Ciudad Autónoma de Melilla and Empresa para la Gestión de Residuos Industriales SA (EMGRISA). Design throughput is 40,000 tpy of MSW.

Photograph courtesy of SIRUSA
Posted 19 Jan 2014

Meruelo
Location: Cantabria
Operator: Urbaser SA
Configuration: 1 X10.5 MW
Operation: 2006
Fuel: refuse
Boiler/incinerator system supplier: Lurgi
T/G supplier: ??

Photograph courtesy of Urbaser SA
Posted 19 Jan 2014

Tirmadrid
Location: Madrid
Operator: Urbaeneregia SA
Configuration: 1 X 29 MW
Operation: 1996
Fuel: refuse
Boiler/incinerator system supplier: Vulcan Sadeco, Lurgi
T/G supplier: ABB
EPC: Holter, Dragados
Quick Facts: The integrated MSW plant treats 1,200 tpd of which about 500 tpd are incinerated in three identical treatment lines with ROWITEC rotating CFB incinerators. The plant was developed by a JV of Enel Unión Fenosa Renovables and Endesa Cogeneración y Renovables. It is located at Valdemíngomez, Madrid.

Photograph courtesy of Lurgi-Lentjes
Posted 21 Aug 2004

Sant Adrià PIVR
Location: Barcelona
Operator: TERSA - Tratamiento y Selección de Residuos SA
Configuration: 1 X 26 MW, 1 X 5.5 MW CHP
Operation: 1975
Fuel: refuse
Boiler/incinerator system supplier: Von Roll
T/G supplier: Alstom, KKK
Quick Facts: The Sant Adrià de Besòs PIVR went into operation in 1975 and was turned over to TERSA in 2011. Throughput for the three-line plant in 2012 was 287,000t. It is adjacent to Endesa's Besos CCGT plant.

Photograph courtesy of TERSA - Tratamiento y Selección de Residuos SA
Posted 19 Jan 2014

Son Reus
Location: Islas Baleares
Operator: TIRME SA
Configuration: 1 X 34 MW
Operation: 1997
Fuel: refuse
Boiler/incinerator system supplier: Deutsche Babcock
T/G supplier: MHI, ABB
Quick Facts: This WTE plant is a partership of Enel Green Power (40%), and FCC, Iberdrola, and Urbaser with 20% shares each. The project derived from a 1990 waste disposal plan for the Balearic Islands culminating in the 1992 award of the WTE project to TIRME. Construction began in Mar 1994 and the two-line plant went into operation in Mar 1997. Throughput is about 300,000 tpy of MSW.

Photograph courtesy of TIRME SA
Posted 18 Jan 2014

Tarragona Sirusa
Location: Tarragona
Operator: SIRUSA - Serveis d’Incineració de Residus Urbans SA
Configuration: 1 X 7.4 MW
Operation: 1989
Fuel: refuse
Boiler/incinerator system supplier: Deutsche-Babcock
T/G supplier: GEC-Alstom
Quick Facts: This two-line WTE serves about 300,000 inhabitants of the municipalities of Cambrils, Constantí, Reus, Salou, Tarragona, and Valls. The operating company was formed in 1990 by Mancomunidad (60%) and IDAE (40%).

Photograph courtesy of SIRUSA
Posted 19 Jan 2014

Tragisa Campdora
Location: Girona
Operator: Trargisa - Tractament de Residus i Aigües residuals del Sistema de Girona SA 
Configuration: 1 X 1.9 MW
Operation: 1984
Fuel: refuse
Boiler/incinerator system supplier: Martin, Aitersa
T/G supplier: ??
Quick Facts: This is the only WTE plant in Girona. Plans are in hand to expand and modernize the facility, increasing througpu about 50% to 45,000 tpy of MSW. At the entrance is a sculpture by Domènec Fita depicting a chimney.

Photograph courtesy of elracodelpare.blogspot.com
Posted 20 Jan 2014

   
Zabalgardi
Location: Vizcaya
Operator: Zabalgarbi SA
Configuration: 1 X 56.5-MW steam set, 1 X 43-MW LM6000 gas turbine
Operation: 2005
Fuel: refuse
Boiler/incinerator system supplier: CNIM
T/G supplier: Nuovo, Jeumont, GE
EPC: Sener, CNIM
Quick Facts: This WTE plant is a partership of three private companies, Sener, FCC, and Kutxabank, with 65% ownership in total, and three public companies,  Diputación Foral de Bizkaia, EVE, and MMI with a 35% share. The unique Sener design uses GT exhause to superheat the incinerator system steam. MSW is obtained from over 100 municipalities in Bizkaia with about 700,000 inhabitants. This refuse is supplemented by rejects from separation and recycling companies. Waste throughput in 2012 was 224,000t.

Photograph courtesy of Grupo FCC
Posted 18 Jan 2014

Abbreviations

Data: industcards, Platts UDI World Electric Power Plants Data Base