Wind Energy Power Plants in the UK - offshore
Beatrice Field
Location: Offshore Rossshire
Operator: Talisman Energy (UK) Ltd
Configuration: 2 X 5-MW 5M
Operation: 2007
WTG supplier: REpower
EPC: AMEC, REpower
Quick facts: In Apr 2005, Talisman Energy and Scottish and Southern awarded AMEC a contract to design and manage delivery of two 5-MW wind turbines for the Beatrice wind farm demonstration project. The scheme demonstrates the feasibility of siting WTGs in deepwater (45m in this instance) at a site 25km offshore and 70km northeast of Inverness in the Beatrice oil field. The first WTG was set in August 2006 and came online in May 2007 with the second following in Aug.

Photograph courtesy of REpower Systems AG
Posted 28 Jan 2007

Blyth Offshore
Location: Offshore Northumberland
Operator: AMEC Border Wind
Configuration: 2 X 2-MW V66
Operation: 2000
WTG supplier: Vestas
Quick facts: These were the first truly offshore WTGs installed in the UK.

Photograph courtesy of AMEC Border Wind
Posted 15 Nov 2003

Burbo Bank
Location: Offshore Lancashire
Operator: Dong (UK) Ltd
Configuration: 25 X 3.6-MW SWT-3.6-107
Operation: 2007
WTG supplier: Siemens Wind
Quick facts: These machines were erected in less than 1.5mos at a site 12km offshore Wallasey in Liverpool Bay, well ahead of schedule. During construction, Siemens leased a 45,000 mē site at Mostyn in North Wales. The 65m steel towers were assembled upright and all systems were tested before they were loaded onto the installation vessel which carried towers, nacelles, hubs and blades for 3 turbines per trip to the site area. Each 500t wind turbine was erected in five heavy lifts with a maximum weight of approximately 185t. The average erection time per turbine was less than half a day.

Photograph courtesy of Siemens
Posted 11 Jul 2007

Greater Gabbard
Location: Offshore Suffolk
Operator: Airtricity Holdings Ltd
Configuration: 140 X 3.6-MW SWT-3.6-107
Operation: 2010
WTG supplier: Siemens Wind Power
EPC: Fluor
Quick facts: Greater Gabbard was completed in Sep 2012 and became the largest offshore winfarm in the world. It is a 50:50 joint venure of Airtricity Holdings (SSE) and RWE npower renewables. The site is 25km offshore the Suffolk coast and is connected via 3 main subsea cables to a 132kV substation at Sizewell.

Photograph courtesy of RWE npower renewables
Posted 12 Sep 2012

Gunfleet Sands
Location: Offshore Norfolk
Operator: Dong Energy UK
Configuration: 48 X 3.6-MW SWT-3.6-107
Operation: 2010
WTG supplier: Siemens Wind Power
EPC: Dong Energy, MT Højgaard
Quick facts: Gunfleet Sands is 7km off the Essex coast opposite Clacton-on-Sea and the subsea cable connection makes landfall just northeast of Holland-on-Sea. The project was first identified in 1996 by Windmaster Developments, acquired by Enron in 2000, purchased by GE in 2002, and then purchased by Dong Energy. Final consents were awarded in Mar 2004 for Phase-I and in Mar 2008 for Phase-II. The turbines are spaced a 435m and the turbine rows are about 890m apart. The total surface area of the site is approximately 15km². The maximum height of the blade tip above sea level is 129m. Due to the very varying water depths the installation was carried out by the use of the large floating crane "Svanen" and the jack-up barge "Excalibur".

Photograph courtesy of Osprey Shipping Ltd
Posted 1 May 2010

Gwynt y Mor
Location: Offshore Abergele
Operator: RWE Innogy GmbH
Configuration: 160 X 3.6-MW SWT-3.6-107
Operation: 2015
WTG supplier: Siemens Wind Power
EPC: Siemens, Bladt Industries, EEW Special Pipe Construction
Quick facts: Gwynt y Mor offshore Caernarfonshire in North Wales was officially inaugurated on 18 Jun 2015 as the world's second largest offshore wind farm. The £2bn WPP was jointly-invested by RWE (60%), Stadtwerke Munchen (30%), and Siemens (10%). The site covers 80kmē and the 150m tall WTGs are installed in waters up to28m deep. The project includes 2 offshore substations and 134km of onshore cable.

Photograph courtesy of Siemens
Posted 18 Jun 2015

Kentish Flats
Location: Offshore Norfolk
Operator: Dong Energy UK
Configuration: 30 X 3-MW V90
Operation: 2005
WTG supplier: Vestas
Quick facts: At completion, this was the largest offshore wind farm in the U.K. and the V90 machines were the largest built in the British Isles as well. Kentish Flats is expected to produce 285 GWh/yr of electricity.

Photograph courtesy of Elsam
Posted 17 Dec 2005

Lincs Offshore
Location: Offshore Lincolnshire
Operator: Lincs Wind Farm Ltd
Configuration: 75 X 3.6-MW SWT-3.6-120
Operation: 2013
WTG supplier: Siemens Wind Power
EPC: Rambøll Danmark A/S, ISC Consulting Engineers A/S, MT Højgaard
Quick facts: The final WTG at Lincs Offshore was installed on 31 Mar 2013. The site is 8km off the coast of Skegness in water depths of 8.5 to 16.3m. Construction was staged from Esbjerg, Denmark. The monopiles weighed from 320-480t. Lincs Wind Farm is a JV of Centrica Energy, DONG Energy and Siemens Project Ventures.

Photograph courtesy of Centrica
Posted 7 Apr 2013

London Array Offshore
Location: Offshore Kent
Operator: London Array Ltd
Configuration: 175 X 3.6-MW SWT-3.6-120
Operation: 2013
WTG supplier: Siemens Wind Power
EPC: COWI, Bilfinger Berger, Per Aarsleff
Quick facts: London Array sited 20km off the east coast of Britain was the world's largest offshore wind plant at completion. The location comprises 245km² of low-tide sand banks marking the entry to the shipping route into London via the Thames. Approximately 10km further in-shore is the Gunfleet Sands wind plan opened in Jun 2010. Development at the London Array began in Feb 2003. Construction on the new onshore substation at Cleve Hill started in Jul 2009 and was completed in Oct 2012. Offshore construction started in Mar 2011, when the first foundation was installed. The first WTG went up in Jan 2012, first power was in Oct 2012 and the final turbine was installed in Dec 2012. It was commissiond at 16.09 on 6 Apr 2013 marking project completion. Offical inauguration was on 4 Jul 2013. London Array is a JV of DONG Energy ( 50%), E.ON (30%), and Masdar (20%). The stated project cost was €2.2bn.

Photograph courtesy of Siemens
Re-posted 5 Jul 2013

Lynn/Inner Dowsing
Location: Offshore Lincolnshire
Operator: Centrica Energy
Configuration: 54 X 3.6-MW SWT-3.6-107
Operation: 2008
WTG supplier: Siemens
EPC: RES, Rambøll A/S, MT Højgaard
Quick facts: The Lynn complex is 5.2km offshore Skegness while Inner Dowsing is 5.2km offshore Ingoldmells. The concessions were acquired by Centrica from RES in Dec 2003 and construction tenders issued in 2006. The final contracts were awarded in Feb 2007 for the offshore and onshore work, including a new substations in Skegness. First power to the grid was in May 2008 and the last machine was installed the following month. Nexans supplied 72km of 36kV HV submarine cable. The projects cost around £300m and Ode was owner's consultant.

Photograph courtesy of Centrica
Posted 4 Apr 2009

North Hoyle
Location: Offshore Flintshire
Operator: RWE npower Renewables
Configuration: 30 X 2-MW V80
Operation: 2004
WTG supplier: Vestas

Photograph courtesy of and copyright by National Wind Power
Posted 5 May 2004

Ormonde
Location: Offshore Cumbria
Operator: Vattenfall Wind
Configuration: 30 X 5-MW 5M
Operation: 2012
WTG supplier: REpower
EPC: Vattenfall, REpower, A2SEA, Agrilek, Harland & Wolff, Askam Construction, Neil Martin Group, R G Parkins
Quick facts: In Feb 2007, DTI approved a unique wind/gas hybrid power scheme centered on the Ormonde Wind Farm in the Irish Sea 10km west of Barrow-in-Furness, Cumbria. Originally, developer Eclipse Energy planned to use the wind plant plus about 50 MW of onshore thermal capacity fueled by gas from the Ormonde South and Ormonde North gas fields. In 2008, Vattenfall bought Eclipse Energy and the scheme moved forward as wind-only. The wind farm is sited on a 8.7km² plot, 10km offshore near Walney Island. Onshore construction works began in Nov 2009 and offshore work started in May 2010, completing in Feb 2011. Full commissioning followed in early 2012

Photograph by Tony West Photography and courtesy of Agrilek Ltd
Posted 16 Oct 2014

Robin Rigg
Location: Offshore Dumfries and Galloway
Operator: E.ON UK Renewables Ltd
Configuration: 60 X 3 MW V90
Operation: 2010
WTG supplier: Vestas
EPC: Vestas, MT Hojgaard
Quick facts: Robin Rigg was commissioned on 16 Apr 2010 as the largest operating offshore wind park in the UK. The project was acquired by E.ON UK Renewables in autumn 2003. The site is in Solvay firth is 9km off Balcary Point and about the same distance from Seaton, Cumbria, where the transmission cables make landfall. The turnkey construction contract was awarded in Dec 2006. Robin Rigg cost about €500mn.

Photograph courtesy of E.ON UK
Posted 17 Apr 2010

Rhyl Flats
Location: Offshore Caernarfonshire (Wales)
Operator: RWE npower renewables
Configuration: 25 X 3.6-MW SWT-3.6-107
Operation: 2009
WTG supplier: Siemens Wind Power
EPC: Rambøll A/S, MT Højgaard
Quick facts: Rhyl Flats was built offshore Abergele, North Wales, in water depths of 6.5 to 12.5m. The design and fabrication of the foundations took place during the second half of 2007, and installation of the foundations was carried out during the spring/summer of 2008.

Photograph courtesy of RWE
Posted 7 Apr 2013

Scroby Sands
Location: Offshore Norfolk
Operator: E.ON UK Renewables
Configuration: 30 X 2-MW V80
Operation: 2004
WTG supplier: Vestas
Quick facts: The Scroby Sands wind farm is in the North Sea, 2.5km off the coast of Great Yarmouth. The 60m turbines are on hollow 4.5m steel towers in from 13 to 20m of water. The tower foundations were piled up to 30m into the sea bed.

Photograph courtesy of and copyright by E.ON UK
Posted 15 Jan 2005

Tees Offshore
Location: Offshore Yorkshire
Operator: EDF Energy Renewables
Configuration: 27 X SWT-2.3-93
Operation: 2013
WTG supplier: Siemens Wind Power
EPC: EDF, Marine Projects International Consultancy and Contracting, Van Oord Dredging and Marine
Quick facts: Offshore work at Tees began in Feb 2012 and the last WTG was installed in Jun 2013 with about half the total in operation. The project was officially opened on 16 Apr 2014. The WTGs are about 1.5km offshore near Redcar.

Photograph by SteveT (Panoramio)
Re-posted 16 Apr-2014

Thanet
Location: Offshore Kent
Operator: Vattenfall Wind
Configuration: 100 X 3-MW V90
Operation: 2010
WTG supplier: Vestas
EPC: Vestas, Vattenfall, A2SEA
Quick facts: When officially opened on 23 Sep 2010, Thanet was the world's largest offshore wind farm. The installation is in the English Channel about 11km offshore Margate. Thanet took 2yrs to build and cost about €880mn. The towers are up to 115m tall and are placed in 10-25m of water over a 35km² site. Two subsea cables manufacture by Prysmian Group connect to an onshore substation at Richborough and this connects to the 132kV grid.

Photograph courtesy of Vattenfall
Posted 9 Oct 2010

West of Duddon
Location: Offshore Cumbria
Operator: Dong Energy UK
Configuration: 108 X 3.6-MW SWT-3.6-120
Operation: 2014
WTG supplier: Siemens
Quick facts: This WPP has a 67km² site in the East Irish Sea, 14km from Walney Island, Cumbria. It is situated in the vicinity of three operational wind farms, Barrow, Walney and Ormonde. The project was awarded to Morecambe Wind Ltd in Dec 2003, a partnership of Elsam, Eurus Energy, and ScottishPower, as part of the UK's Round 2 offshore development program. Section 36 consent wss in Sep 2008 and a 50:50 Joint Operations Agreement was signed in Mar 2010 between SP Renewables and DONG Energy. The FID for the £1.6bn project was in Jun 2011. First electricity was generated in Jan 2014 and the plant was declared complete on 30 Oct 2014, about 2mos ahead of schedule. The Pacific Orca and the Sea Installer were used for the installation.

Photograph courtesy of worldmaritimenews.com
Posted 21 Nov 2014

Abbreviations

Data: industcards, Platts UDI World Electric Power Plants Data Base

Updated 27-Dec-2016

Home