Wind Energy Plants in Poland
Banie Kozielice
Location: Zachodnio-Pomorskie
Operator: Energix Renewables Energies
Configuration: 25 X 2-MW V100
Operation: 2016
WTG supplier: Vestas
Quick facts: This is the first phase fof the 192-MW Banie complex acquired by Energix in Mar 2015. The total financing for the first phase is up to PLN 270mn with financing of up to PLN 150mn from the EBRD.

Photograph courtesy of Energix Renewables Energies
Posted 22 Dec 2015

Bardy-Dygowo
Location: Zachodnio-Pomorskie
Operator: ENEA SA
Configuration: 25 X 2-MW SWT-2.3-V90
Operation: 2012
WTG supplier: Vestas
EPC: Vestas
Quick facts: This WPP was developed by Vestas and acquired by ENEA in Apr 2012 for an udisclosed sum.

Photograph courtesy of ENEA SA
Posted 9 Sep 2015

Kamiensk
Location: Lodzkie
Operator: PGE Energia Odnawialna SA
Configuration: 15 X 2-MW E70
Operation: 2007
WTG supplier: Enercon

Photograph courtesy of Elektrownia Wiatrowa Kamiensk Spolka
Posted 1 Mar 2008

Karnice
Location: Zachodnio-Pomorskie
Operator: Energa
Configuration: 13 X 2.3-MW SWT-2.3-93
Operation: 2010
WTG supplier: Siemens
Quick facts: The Karnice wind park is in the northwestern Poland about 5km from the Baltic Sea. It was developed by DONG Energy.

Photograph courtesy of DONG Energy
Posted 5 Feb 2011

Koniecwald
Location: Pomorskie
Operator: PGE Energia Odnawialna SA
Configuration: 12 X 1.5-MW sle
Operation: 2008
WTG supplier: GE Wind
Quick facts: This wind plant is near Sztum, also known as Malbork. Developed by Iberdrola Energia Odnawialna, sold to PGE in Feb 2013.

Photograph by mczajek (Panoramio)
Posted 17 May 2011

Puck
Location: Pomorskie
Operator: Polish Energy Partners SA
Configuration: 11 X 2-MW G80
Operation: 2007
WTG supplier: Gamesa
EPC: Gamesa
Quick facts: In Dec 2005, Gamesa signed its first WTG contract in Poland for this project is in Lebcz (Puck) in Pomorskie. The contract was for approximatley €24mn.

Photograph courtesy of Gamesa
Posted 27 Dec 2011

Suwalki
Location: Podlaskie
Operator: RWE
Configuration: 18 X 2.3-MW SWT-2.3-93
Operation: 2009
WTG supplier: Siemens
Quick facts: This plant was completed in Jul 2009 with the largst machines and tallest towers (100m) yet deployed in Poland. The project was one of two acquired by RWE from Polish Energy Partners.

Photograph courtesy of RWE
Posted 27 Jan 2011

Tymien
Location: Zachodnio-Pomorskie
Operator: Invenergy Enerco Joint Venture
Configuration: 25 X 2-MW V80
Operation: 2006
WTG supplier: Vestas
EPC: MDI Sp zoo
Quick facts: The Tymien site is about 5km from the Baltic coast in Zachodnio-Pomorskie.

Photograph courtesy of MDI Sp zoo
Posted 29 Oct 2011

Wicko
Location: Pomorskie
Operator: Tauron Ekoenergia
Configuration: 20 X 2-MW V90
Operation: 2013
WTG supplier: Vestas
EPC: Grupo Aldesa
Quick facts: The EPC contract for this WPP was signed in Jun 2012. The cost was zl243.8mn. The project completed 28 Oct 2013.

Photograph courtesy of Tauron
Posted 17 May 2014

Abbreviations

Data: industcards, Platts UDI World Electric Power Plants Data Base

Updated 22-Dec-2015