Coal-Fired Plants in China - Henan

Datang Xinyang
Location: Henan
Operator: Datang Xinyang Power Generation Co Ltd
Configuration: 2 X 300 MW, 2 X 660 MW
Operation: 2001-2009
Fuel: bituminous coal
Boiler supplier: Shanghai, Dongfang
T/G supplier: Dongfang, Harbin
EPC: China Power Complete Equipment Co Ltd, Henan No 1 Thermal Power Construction Co, Northwest Electric Power Design Institute, China Construction Second Engineering Bureau Ltd
Quick facts: In 1995, a new company was formed to build a pair of 300-MW generating units in Pingqiao district, Xinyang City. These were placed in service in Jun and Nov 2001, respectively. In Jan 2003, the company was placed under the management of China Datang, which shortly began implementation of Henan’s first USC units as Xinyang Phase-II. These were approved by NDRC in Mar 2008 and Xinyang Unit-3 completed in Oct 2009 after 18mos of construction with the second set following not long thereafter. The Phase-II project cost Rmb 4.34bn. The plant connects to the 220kV and 500kV grids. Shaanxi Coal Chemical Group now owns 51% of the plant.

Photograph courtesy of China Datang Corp
Posted 14 Aug 2016

Dengfeng
Location: Henan
Operator: China Resources Power Holdings Co
Configuration: 2 X 300 MW
Operation: 2004
Fuel: coal
Boiler supplier: ??
T/G supplier: ??
Quick facts: Dengfeng is 85% owned by CR Power. Construction started in Dec 2002 and took approximately 20mos, about 6mos ahead of the average construction time for similar generation units in the Chinese power industry.

Photograph courtesy of China Resources Power Holdings Co
Posted 6 Nov 2004

Hebi Wanhe/Hebi Fenghe
Location: Henan
Operator: Hebi Wanhe Electric Power Co Ltd/Hebi Fung Hok Power Co Ltd
Configuration: 2 X 200 MW, 2 X 300 MW, 2 X 600 MW
Operation: 1991-2007
Fuel: coal
Boiler supplier: Harbin, Dongfang, BHDB
T/G supplier: ??
EPC: Henan No 1 Thermal Power Construction, Henan No 2 Thermal Power Construction Co

Photograph by 鹤壁电厂 (Panoramio)
Posted 17 Jul 2010

Heqi
Location: Henan
Operator: Henan Investment Group Co Ltd
Configuration: 2 X 660 MW
Operation: 2015-2016
Fuel: coal
Boiler supplier: Dongfang
T/G supplier: Dongfang
EPC: Henan Electric Power Survey & Design Institute, Henan First Thermal Power Construction
Quick facts: This USC PS in Heqi County, Hebi City, was included in Henan's 2014 key projects construction program. The plant capex is Rmb 5bn. Unit-1 went commercial on 5 Dec 2016 after about 2yrs of construction. Plant production is expected to be about 6 TWh/yr.

Photograph courtesy of www.hebiw.com
Posted 20 Mar 2016

Huaneng Qinbei 1-4
Location: Henan
Operator: Huaneng Power International Inc
Configuration: 4 X 600 MW
Operation: 2004-2008
Fuel: coal
Boiler supplier: BHDB, Dongfang
T/G supplier: Harbin
EPC: Henan Construction Group II
Quick facts: Unit-1 was the first domestically-made 600-MW supercritical coal-fired generating unit put into operation. In Jun 2007, HPI received approval to extend the Qinbei plant with Units 3&4. The project cost approximately RMB4.48, of which 20% was equity capital funded by HPI (60%), Henan Provincial Construction Investment Corp (35%), and Jiyuan Municipal Construction Investment Corp (5%), with the remaining funded by bank loans. In Dec 2010, HPI was approved to add the first of two 1,000-MW sets at Qinbei.

Photograph courtesy of Henan Construction Group II
Posted 17 Jul 2010

Kaifeng-2
Location: Henan
Operator: China Power Investment Corp
Configuration: 2 X 600 MW
Operation: 2008-2009
Fuel: bituminous coal
Boiler supplier: Babcock-Hitachi Dongfang Boiler Co
T/G supplier: Dongfang
EPC: CPI Power Engineering Co, Henan No 2 Thermal Power Construction Co,
Quick facts: This supercritical power station is located east of Kaifeng City proper and connects to the 500kV grid. It is jointly invested by CPI (51%), Shenzhen Energy Group Co., Ltd. (43%) and Kaifeng City Construction Investment Co (6%). The estiamted cost was 4,560mn yuan. Coal is from Zhengzhou Coal Industry Co Ltd.

Photograph courtesy of www.eccl.com.cn
Posted 10 Nov 2012

Luohe-2
Location: Henan
Operator: Huadian Power International Corp Ltd
Configuration: 2 X 300 MW CHP
Operation: 2010
Fuel: coal
Boiler supplier: Shanghai
T/G supplier: ??
EPC: SEPCO
Quick facts: Huadian is a 75% owner of this plant. Unit-1 went online on 14 Jul 2010.

Photograph courtesy of Henan Land Cement Co
Posted 5 Dec 2010

Minquan
Location: Henan
Operator: China Guodian Corp
Configuration: 2 X 600 MW
Operation: 2010
Fuel: bituminous coal
Boiler supplier: Babcock-Hitachi Dongfang Boiler Co
T/G supplier: Dongfang
EPC: Henan No 1 Thermal Power Construction Co,
Quick facts: This supercritical power station is Minquan County, 33km east of Shangqiu City. The plant is invested by China Guodian (51%), Yongcheng Coal & Electricity Holding Group Co Ltd (20%), Henan Shenhuo Group Co Ltd. (20%) and Minquan County Oasis Investment Co Ltd (9%) The project officially started construction on 26 Sep 2006 and Unit-1 went commercial on 23 Aug 2008.

Photograph courtesy of China Guodian Corp
Posted 10 Nov 2012

Pingdingshan
Location: Henan
Operator: China Power Investment Corp
Configuration: 1 X 50 MW, 2 X 210 MW
Operation: ??-2006
Fuel: coal
Boiler supplier: ??
T/G supplier: ??
Quick facts: The 210-MW units have wet limestone scrubbers from CPI Yuanda.

Photograph courtesy of CPI Yuanda Environmental
Posted 30 Dec 2007

Pingdingshan Luyang
Location: Henan
Operator: China Power Investment Corp
Configuration: 2 X 1,000 MW
Operation: 2010
Fuel: bituminous coal
Boiler supplier: Dongfang
T/G supplier: Harbin
EPC: Henan No 1 Thermal Power Construction Co
Quick facts: These USC units were CPI's first 1-GW sets in inland China. The site plan calls for six units to be built in partnership with Pingdingshan Coal Co Ltd. Unit-1 was the first installation of Emerson's Ovation system for direct turbine control in a 1,000-MW set.

Photograph courtesy of Henan Land Cement Co
Posted 5 Dec 2010

Shuangyashan
Location: Heilongjiang
Operator: Guodian Shuangyashan Power Generation Co Ltd
Configuration: 2 X 200 MW, 2 X 210 MW
Operation: 1988-1992
Fuel: bituminous coal
Boiler supplier: Harbin, Taganrog
T/G supplier: Harbin, LMZ, Electrosila
EPC: Harbin
Quick facts: This was the largest power station in the province when completed.

Photograph courtesy of Fubang Technology Industrial
Posted 5 Jul 2009

Xinmi Yuzhong
Location: Henan
Operator: SDIC Sanjili Energy Co
Configuration: 2 X 300 MW, 2 X 1,000 MW
Operation: 2006-2012
Fuel: coal
Boiler supplier: Shanghai
T/G supplier: Shanghai, Dongfang
EPC: East China Electric Power Design, Shanghai Power Const Engineering, Henan Electric Power Survey & Design Inst, Henan No 2 Thermal Power Co
Quick facts: On 16 Sep 2009, the foundation stone laying ceremony was held for Phase-II of the Henan Xinmi power station at the 38ha site in Zhengzhou City. This represents an investment of 8,384mn yuan. Unit-4 completed its 168hr test run on 30 Jul 2012, bringing the expansion project to completion.

Photograph courtesy of Henan No 2 Thermal Power Co
Posted 8 Aug 2012

Xinxiang Baoshan
Location: Henan
Operator: Huadian Power International
Configuration: 2 X 660 MW
Operation: 2007
Fuel: bituminous coal
Boiler supplier: Babcock-Hitachi Dongfang Boiler Co
T/G supplier: Shanghai
EPC: SEPCO, Henan No 1 Thermal Power Co
Quick facts: Unit-1 went commercial on 31 Mar 2007 and Unit-2 on 22 Aug 2007.

Photograph courtesy of Huadian Power Internaional
Posted 26 May 2010

Xinxiang Yuxin
Location: Henan
Operator: China Power Investment Corp
Configuration: 2 X 300 MW CHP
Operation: 2006
Fuel: coal
Boiler supplier: Wuhan
T/G supplier: Shanghai
Quick facts: These units have wet limestone scrubbers from CPI Yuanda.

Photograph courtesy of CPI Yuanda Environmental
Posted 30 Dec 2007

Yahekou-I
Location: Henan
Operator: Nanyang Yahekou Electric Power Co Ltd
Configuration: 2 X 350 MW
Operation: 1998-1999
Fuel: bituminous coal
Boiler supplier: Babock & Wilcox Espanola
T/G supplier: ABB
EPC: INITEC, China Machine New Energy Co, Henan Lixin Power Construction Supervision
Quick facts: In Nov 1998, the first 350-MW unit at the Yahekou plant went into service in Nanyang City, southwestern Henan. The second followed in Jun 1999. The Spanish government made $372mn in loans to support the project. The plant is mainly invested by Henan Construction Investment and Investment. In 2005, a second phase with two 600-MW units was launched and these came online in 2008.

Photograph courtesy of Zhengzhou Electric Power College of Power Engineering
Posted 28 Aug 2011

 
Zhumadian Gucheng
Location: Henan
Operator: China Resources Power Holdings Co Ltd
Configuration: 2 X 300 MW
Operation: 2006
Fuel: bituminous coal
Boiler supplier: Harbin
T/G supplier: Dongfang
EPC: Jiangsu First Electric Power Construction Co
Quick facts: In March 2005, CR Power announced that the NDRC had approved construction of two 300-MW units at Zhumadian Gucheng power station in Zhumadian City.

Photograph courtesy of Jiangsu First Electric Power Construction Co
Posted 8 Mar 2014

Yaomeng
Location: Henan
Operator: China Power International Development Ltd
Configuration: 1 X 310 MW, 3 X 300 MW, 2 X 600 MW
Operation: 1975-2007
Fuel: bituminous coal
Boiler supplier: Shanghai Boiler Works-Mitsui Babcock, Cockerill-Combustion Engineering, Babcock-Hitachi Dongfang Boiler
T/G supplier: Shanghai, Alsthom, Harbin
EPC: Henan Electric Power Survey & Design Institute, Henan No 1 Thermal Power Construction, Henan No 3 Thermal Power Construction, China Machine New Energy
Quick facts: Yaomeng Phase-I in the suburbs of Pingdingshan City has four 300-MW coal-fired units. UNits 1&2 were the first domestically-designed 300-MW coal-fired units online in China. After about 20yrs of operation, the decision was made to rebuild the Unit 1&2 boilers to attain modern performance levels. In Nov 2000, Mitsui Babcock was awarded the rebuild contract and undertook the project in cooperation with China Power Complete Equipment Co and Henan Provincial Electric Power Design Institute. The first unit was completed in 2002 and the second in 2009. In Jan 2006, CPI reported NDRC approval of two 600-MW supercritical boilers to extend Yaomeng PS. The first unit went commercial in Oct 2007 and the second in Dec 2007.

Photograph courtesy of Huangshan Zhungda Power Engineering Co Ltd
Posted 5 Feb 2014

Abbreviations

Data: industcards, Platts UDI World Electric Power Plants Data Base