Coal-Fired Plants in China - Heilongjiang
Datang Harbin No 1
Location: Heilongjiang
Operator: Datang Heilongjiang Power Generation Co Ltd
Configuration: 2 X 300 MW CHP
Operation: 2009
Fuel: lignite
Boiler supplier: Harbin
T/G supplier: Harbin
EPC: Heilongjiang Electric Power Survey and Design Institute, Heilongjiang Power Construction No 1 Co
Quick facts: Construction at this plant started in Nov 2007. Unit-1 went into operation in Nov 2009. This was one of the first Chinese plants with flue gas exhaust through the cooliing towers.

Photograph courtesy of Heilongjiang Power Construction No 1 Co
Posted 26 Jan 2014

Datang Qitaihe
Location: Heilongjiang
Operator: Datang Heilongjiang Power Generation Co Ltd
Configuration: 2 X 350 MW CHP, 2 X 600 MW
Operation: 2001-2008
Fuel: bituminous coal
Boiler supplier: Harbin
T/G supplier: GE, Harbin
EPC: Mitsui, Heilongjiang Power Construction No 1 Co, Datang Power Engineering, Heilongjiang Power Construction No 3 Co
Quick facts: Construction at Qitaihe Phase-I began in Nov 1997. The two units cost 4.27bn yuan and were partially funded by an ABD loan. Phase-II cost 4.7nn yuan. Unit-3 commissioned on 24 Aug 2008 and Unit-4 in Dec 2008. The second-phase stack is 240m tall.

Photograph courtesy of China Datang Corp
Posted 26 Jan 2014

Heilongjiang Qiqihar
Location: Heilongjiang
Operator: China Huadian Group Corp
Configuration: 2 X 300 MW CHP
Operation: 2007-2008
Fuel: bituminous coal
Boiler supplier: Harbin
T/G supplier: Harbin
EPC: Heilongjiang Power Construction No 1 Co
Quick facts: Groundbreaking for the TPP was on 25 Aug 2005. Unit-1 went commercial on 27 Aug 2007 and Unit-2 followed in Nov 2007, somewhat ahead of schedule.

Photograph courtesy of Heilongjiang Power Construction No 1 Co
Posted 19 Oct 2014

Huaneng Yichun
Location: Heilongjiang
Operator: China Huaneng Group Corp
Configuration: 2 X 350 MW CHP
Operation: 2015
Fuel: coal
Boiler supplier: Harbin
T/G supplier: Harbin
EPC: Northeast Electric Power Design Institute, Heilongjiang Power Construction No 3 Co
Quick facts: This supercritical cogen plant is in a new industrial area of Wumahe district, Yichun Prefecture. Ground-breaking was on 5 Jul 2012 and Unit-1 commissioned in Oct 2015, followed by Unit-2 on 21 Dec 2015.

Photograph courtesy of Heilongjiang Power Construction No 3 Co
Posted 22 Jan 2016

Jixi-1 No 8&9
Location: Heilongjiang
Operator: Datang Jixi Thermal Power Co Ltd
Configuration: 2 X 125 MW CHP
Operation: 2002
Fuel: coal
Boiler supplier: Harbin
T/G supplier: ??
Quick facts: This power station is in Didao distict, Jixi City, and it was founded in 1938. Rebuilding began in 1949 and after four expansion projects capacity reached 192 MW. These units have been retired. Work started on a pair of 125-MW sets in 2000 and these came online at the end of 2002. Both units were retrofit with FGD scrubbers.

Photograph courtesy of www.dcywlm.com
Posted 26 Oct 2016

Jixi-2
Location: Heilongjiang
Operator: Datang Jixi Thermal Power Co Ltd
Configuration: 2 X 300 MW CHP
Operation: 2011
Fuel: gangue
Boiler supplier: Harbin
T/G supplier: Harbin
Quick facts: This CFB project is a 60:40 JV of China Datang and Heilongjiang Electric Power Development Co. Preparatory work began in Sep 2004, NDRC approval was in May 2009, and full construction began in Jun 2009. Unit-1 completed its trial operation on 25 Jun 2011. The total approved investment was CNY 282,052mn.

Photograph courtesy of www.dcywlm.com
Posted 26 Oct 2016

 
Mudanjiang-II
Location: Heilongjiang
Operator: China Huadian Group Corp
Configuration: 4 X 100 MW (ret), 2 X 215 MW, 1 X 200 MW, 2 X 300 MW CHP
Operation: 1981-2011
Fuel: bituminous coal
Boiler supplier: Harbin, Taganrog
T/G supplier: Harbin, LMZ, Electrosila
EPC: Harbin
Quick facts: In Jul 2007, China Huadian published the feasibility study for a 600-MW replacement for the Mudanjiang No 2 CHP plant in Mudanjiang City. The work was done by China International Engineering Consulting, CHEC, and Northeast Electric Power Design Institute. Construction began in Jul 2008 and official NDRC approval was received in Dec 2008. Harbin was the BTG supplier for two 300-MW subcritical sets and these commissioned in Dec 2010, and Jan 2011, respectively. At that time, four 100-MW units built from 1981-1985 were closed.

Photograph courtesy of China Huadian Group Corp
Posted 4 Mar 2012

Shuangyashan
Location: Heilongjiang
Operator: Guodian Shuangyashan Power Generation Co Ltd
Configuration: 2 X 200 MW, 2 X 210 MW
Operation: 1988-1992
Fuel: bituminous coal
Boiler supplier: Harbin, Taganrog
T/G supplier: Harbin, LMZ, Electrosila
EPC: Harbin, Heilongjiang Power Construction No 1 Co
Quick facts: This was the largest power station in the province when completed.

Photograph courtesy of Fubang Technology Industrial
Posted 5 Jul 2009

Abbreviations

Data: industcards, Platts UDI World Electric Power Plants Data Base

Updated 26-Oct-2016