Hydroelectric Power Plants in Vietnam - Ha Giang & Lao Cai
Bac Ha
Location: Lao Cai
Operator: Bac Ha Hydropower JSC
Configuration: 2 X 45 MW Francis
Operation: 2012
T/G supplier: Tianfa
EPC: . Norinco International/VEIC - Vietnam Electronics and Informatics Corp, PECC No 1, Licogi
Quick facts: In Feb 2005, Vietnam’s Infrastructure Development and Construction Corp (Licogi) broke ground on the 90-MW Bac Ha dam and hydroelectric project. In Feb 2006, Agribank said it would loan $53mn for the plant. This was the first HPP that Agribank fully financed. The $104mn project is on the Chay River and is expected to have an average output of 370 GWh/yr. The first unit went into operation in Jun 2012, about 3yrs past the original schedule.

Photograph courtesy of Licogi
Posted 25 Nov 2014

Coc San
Location: Lao Cai
Operator: Nexif Energy Management Pte Ltd
Configuration: 3 X 11-MW Pelton
Operation: 2016
T/G supplier: ??
EPC: Zhejiang Hydropower Construction & Installation Co Ltd
Quick facts: This run-of-the-river HPP is in the Dum River Valley, a tributary of the Hong (Red) River, in Tong Xanh commune, Bat Xat district, about 300km northwest of Hanoi. The project went commercial in April 2016 and is operating under the Avoided Cost Tariff regime. Nexif led the development of the The project was initially developed by InfraCo Asia, a company of the Private Infrastructure Development Group (PIDG). It has a 25m tall gravity dam for peak period storage, a 5.6km HRT, and a surface powerhouse. In February 2016, Nexif Energy took a controlling interest in the project through the acquisition of a majority ownership of Viet Hydro Pte Ltd, the controlling shareholder in the project.

Photograph courtesy of Nexif Energy Management Pte Ltd
Posted 25 Apr 2016

Nam Ngan
Location: Ha Giang
Operator: Song Da Construction Co Ltd
Configuration: 2 X 5 MW Francis
Operation: 2010
T/G supplier: Hunan Shaoyang Zijiang Hengyuan Hydroelectric Equipment Manufacture
EPC: Song Da Construction
Quick facts: Nam Ngan is located on Nam Ngan stream between Viet Lam and Quang Ngan communes, Vi Xuyen district. The project's estimated annual production is 58 GWh. The plant is connected to the national grid with a tie-line to the Ha Giang-Bac Quang 110kV line.

Photograph courtesy of Guizhou CVC
Posted 27 Dec 2011

Nam Tha-6
Location: Lao Cai
Operator: Phuc Khanh Energy Development and Construction Investment Co Ltd
Configuration: 2 X 2.1 MW Francis
Operation: 2012
T/G supplier: Asia-Pacific Power-Tech Co Ltd
Quick facts: Nam Ngan is located on Nam Ngan stream between Viet Lam and Quang Ngan communes, Vi Xuyen district. The project's estimated annual production is 58 GWh. The plant is connected to the national grid with a tie-line to the Ha Giang- Bac Quang 110kV line.

Photograph courtesy of Asia-Pacific Power-Tech Co Ltd
Posted 26 Jun 2013

Ngoi Xan-2
Location: Lao Cai
Operator: Nam Tien Construction Investment & Trading JSC
Configuration: 3 X 3.8 MW Pelton
Operation: 2008
T/G supplier: Asia-Pacific Power-Tech Co Ltd

Photograph courtesy of Asia-Pacific Power-Tech Co Ltd
Posted 26 Jun 2013

Nho Que-2
Location: Ha Giang
Operator: Nho Que Power Development and Investment JSC
Configuration: 2 X 24 MW
Operation: 2016
T/G supplier: ??
EPC: PECC No 1Song Da
Quick facts: This HPP is in Lung Pu commune, Meo Vac district. Construction began in Jun 2014 and the project completed its 72hr test run on 25 Aug 2016 and went into commercil operation. The operator is part of Bitexco Group. The investment was VND 1.5tn.

Photograph courtesy of Bitexco Group
Posted 16 Apr 2017

Nho Que-3
Location: Ha Giang
Operator: Bitexco-Nho Que JSC
Configuration: 2 X 55 MW Francis
Operation: 2012
T/G supplier: Chongqing
EPC: PECC No 4, Cavico
Quick facts: In Sep 2007, the final environmental report was approved for this HPP on the Nho Que River in Lung Pu, Son Vi, Khau Vai and Can Chu Phin communes, Meo Vac district. Construction started in Apr 2008 and, in Dec 2008, the equipment supply contract was signed. The units completed in Apr and Jun 2012, respectively, and connect to the grid at 220kV. Annual production is expected to be about 500 GWh. The total project cost was about VND 2,462bn.

Photograph courtesy of Electricity of Vietnam
Posted 2 Nov 2013

Seo Chong Ho
Location: Lao Cai
Operator: Northern Power Corp
Configuration: 2 X 11 MW Pelton
Operation: 2013
T/G supplier: Kunming
EPC: Hydrochina Zhongnan Engineering Corp, Sinohydro
Quick facts: This HPP is on Seo Chong Ho stream, a tributary of the Ngoi Bo River, in Ta Van and Ban Ho communes, Sa Pa district. The design contract was signed on 7 Nov 2007. The scheme has a 40.5m tall dam forming a 58ha reservoir, a 3.7km diversion tunnel, and then a 2.3km penstock. A 20km, single-circut 110kV tie-line was built to a transformer station on the Lao Cai-Phong Tho transmission line.

Photograph courtesy of PowerChina
Posted 25 Jan 2015

Song Mien
Location: Ha Giang
Operator: Bat Dai Son Hydropower JSC
Configuration: 2 X 3 MW Kaplan
Operation: 2011
T/G supplier: ??
EPC: Song Da No 11 JSC
Quick facts: This SHP project is on the Mien River, a branch of the Lo RIver, in Bat Dai Son commune, Quan Ba district, and Na Khe commune, Yen Minh district. Construction began in Apr 2009 and the plant went commercial in Oct 2011 at a cost of VND 145bn. The project is invested by PetroVietnam Financial JSC.

Photograph courtesy of Electricity of Vietnam
Posted 20 Feb 2012

This was photograph number 6,500 posted in the Power Plants Around the World gallery

Song Mien-5
Location: Ha Giang
Operator: Song Mien 5 Hydro Power JSC
Configuration: 2 X 8.25-MW Francis
Operation: 2012
T/G supplier: ??
EPC: Chinese Water Resources Construction Co
Quick facts: This HPP is on the Mien River, in Vi Xuyen district. The plant started construction in Feb 2010 and went commercial in Oct 2012. The capex was VND 600bn and production is expected to be about 70 GWh/yr.

Photograph courtesy of www.baohagiang.vn
Posted 8 Apr 2017

Song Mien-5A
Location: Ha Giang
Operator: Song Mien 5 Hydro Power JSC
Configuration: 2 X 4.5-MW Francis
Operation: 2015
T/G supplier: Kunming
Quick facts: Song Mien-5A suplies about 35 GWh/yr. The Song Mien HPPs connect to the 110kV grid.

Photograph courtesy of www.baohagiang.vn
Posted 16 Apr 2017

Song Pha
Location: Ha Giang
Operator: Ham Thuan-Da Mi-Da Nhim Hydro Power Co
Configuration: 2 X 3.75 MW Francis
Operation: 1994
T/G supplier: Guizhou CVC

Photograph courtesy of Guizhou CVC
Posted 27 Dec 2011