Hydroelectric Plants in the Czech Republic - other kraj
Bulhary
Location: Jihomoravsky
Operator: RenoEnergie as
Configuration: 2 X 360 kW S-Turbine
Operation: 2007
T/G supplier: Hydrohrom
EPC: Hydroka, Metrostav
Quick facts: This minihydro was built on an existing weir and has a complex fish handling system. Construction began in Jul 2006 and was essentially completed in Oct 2007. Output is expected to be about 3 GWh/yr.

Photograph courtesy of RenoEnergie as
Posted 21 Jun 2009

Cenkova Pila
Location: Plzensky
Operator: CEZ as
Configuration: 1 X 900 kW Francis
Operation: 1909
T/G supplier: Voith, BBC
EPC: BBC
Quick facts: In the mid-1800s, Prague entrepreneur Cenek Bubenicek founded a saw-mill and a lumber-yard at this location. In 1908, the mill was modernized and three water wheels were installed, two to run frame saws for timber processing and the third for wood-working machinery. The town of Kasperske Hory took over the facility and applied to the local Susice district office for  permission to build a power plant. An order was places with Brown-Boveri in Vienna for the electromechanical equipment and installation. The generator and automatic voltage control system were very advanced for the time. Water passes through an open diversion channel into a 50m water-conduit bridge before entering the powerhouse. The building is registered as a listed historical building by the Czech Ministry of Culture.

Photograph courtesy of CEZ as
Posted 1 Aug 2008

Klecany
Location: Praha
Operator: Povodi Vltavy SP
Configuration: 2 X 400 kW S-Turbine
Operation: 2001
T/G supplier: Hydrorhom
EPC: Metrostav AS
Quick facts: This refurbished low-head site is on the Vltava River close to Prague. The 2.3m diameter turbines operate at approximately 2.5m head.

Photograph courtesy of Hydrolink
Posted 10 May 2003

Kromeriz
Location: Moravskoslezsky
Operator: Energo-Pro as
Configuration: 3 X 930 kW Kaplan
Operation: ??
T/G supplier: ??

Photograph courtesy of Energo-Pro as
Posted 27 Dec 2010

Les Kralovstvi Rebuild
Location: Východočeský
Operator: Hydrocez as
Configuration: 2 X 1.06 MW Francis
Operation: 2005
T/G supplier: CKD
Quick facts: This minihydro plant is on the Labe (Elbe) River where two Francis turbines (1.12 MW total) were installed in 1923. The rebuild project included two modern horizontal Francis turbines and synchronous generators, a new control room, and a new control system.

Photograph courtesy of CKD
Posted 22 Aug 2007

Lipno-I
Location: Jihočeské
Operator: CEZ as
Configuration: 2 X 60 MW Francis
Operation: 1959-1961
T/G supplier: CKD
Quick facts: At 44km long and up to 14km wide, the Lipno reservoir on the Vltava River is the largest artificial lake in the Czech Republic. It is formed by a 26m earthfill and gravity dam. The powerhouse is 160m underground and discharges through a 3.6km tunnel. The plant is connected to the grid at 22kV.

Photograph courtesy of CEZ as
Posted 2 Apr 2006

Lipno-II
Location: Jihočeské
Operator: CEZ as
Configuration: 1 X 1.5 MW Kaplan
Operation: 1957
T/G supplier: ??
Quick facts: Lipno II is a run-off-river power station at an 11.5m dam that balances runoff from the upstream Lipno I plant. Lipno II  is fully automatic and remotely controlled from the control centre at Stechovice and from Lipno I.

Photograph courtesy of CEZ as
Posted 2 Apr 2006

Miřejovice
Location: Jihočeské
Operator: Energo-Pro as
Configuration: 3.5 MW Francis
Operation: 1928
T/G supplier: ??
Quick facts: Construction on this SHP began in 1924 and was completed in 1928. The five original turbines were rehabilitated in a project starting in Jul 2009.

Photograph by kvetos (Panoramio)
Posted 27 Dec 2010

Mohelnice
Location: Olomoucky
Operator: CEZ as
Configuration: 1 X 200 kW Francis
Operation: 1914
T/G supplier: Kohout

Photograph courtesy of CEZ as
Posted 29 Sep 2004

Modrany
Location: Praha City
Operator: CEZ as
Configuration: 3 X 540 kW S-turbine
Operation: 1989
T/G supplier: CKD

Photograph courtesy of CEZ as
Posted 22 May 2006

Mohelno
Location: Vysocina
Operator: CEZ as
Configuration: 1 X 1,200 kW, 1 X 600 kW
Operation: 1977-1999
T/G supplier: CKD, Skoda

Photograph courtesy of CEZ as
Posted 22 May 2006

Písek
Location: Jihočeské
Operator: E.ON Trend sro
Configuration: 1 X 315 kW Kaplan
Operation: 1951
T/G supplier: Šmeralovy závody, CKD
Quick facts: This is one of three SHPs on the Otavy River in Pisek. This facility is on the river's right bank in the the Nového Mostu district. The turbine is from the Šmeralovy factory in Brno, a regional post-war leader in advancing the turbine design of Viktor Kaplan.

Photograph courtesy of E.ON Trend sro
Posted 14 Apr 2013

Prelouc
Location: Pardubicky
Operator: CEZ as
Configuration: 2 X 493-kW Francis, 2 X 677-kW Kaplan
Operation: 1926-2003
T/G supplier: Josef Prokop, Strojirny Brno
EPC: HYDROPOL
Quick facts: This SHP is at Km 116 on the River Elbe. In 2003, two of the four original Prokop Francis sets were removed and replaced with larger Kaplan machines.

Photograph courtesy of INGOS sro
Posted 14 Feb 2017

Rimov Rebuild
Location: Jihocesky
Operator: Povodi Vltavy sp
Configuration: 1 X 780-kW, 1 X 400-kW Francis
Operation: 2010
T/G supplier: Strojirny Brno
Quick facts: This SHP on the Rimov Reservoir was originally built in 1986. The turbines were exchanged in 1992 and 1996, respectively, and the plant reconstructed in 2011. The rebuild civil work was by DV stav sro.

Photograph courtesy of INGOS sro
Posted 14 Feb 2017

Soběnov
Location: Jihočeské
Operator: E.ON Trend sro
Configuration: 2 X 736 kW Francis
Operation: 1924
T/G supplier: Kolben, CKD
Quick facts: This is said to be the oldest hydropower plant in South Bohemia. The dam on the Cerna River was badly damaged by heavy flooding in 2002. The dam was strengthened and repaired and put back in service. A 557m, 1.35m diameter power tunnel delivers water to the surface powerhouse and two horizontal T/G sets.

Photograph courtesy of E.ON Trend sro
Posted 14 Apr 2013

Smirice
Location: Kralovehradecky
Operator: Energo-Pro as
Configuration: 2.4 MW Kaplan
Operation: 1953
T/G supplier: ??
Quick facts: This SHP was built at an lock and dam structure completed in 1952 at Km 172 on the River Elbe. The plant was rebuilt in 2011/12.

Photograph courtesy of INGOS sro
Posted 14 Feb 2017

Spalov
Location: Liberecky
Operator: CEZ Obnovitelne Zdroje
Configuration: 2 X 1.2 MW Francis
Operation: 1926
T/G supplier: HYDROPOL
Quick facts: Water passes from a gate system on the Jizera River near Bitouchov weir through a 1.32km tunnel and a 550m mountainside canal into an equalizing water basin and finally through a 60m steel feeder canal into the powerhouse. In Mar 1998, Spalov was modernized.

Photograph courtesy of CEZ as
Posted 1 Aug 2008

Stvanice
Location: Praha
Operator: CEZ as
Configuration: 3 X 1.73 MW S-turbine
Operation: 1987
T/G supplier: CKD, Skoda

Photograph courtesy of CEZ as
Posted 22 May 2006

Vir-I
Location: Vysocina
Operator: E.ON Trend sro
Configuration: 1 X 6 MW, 1 X 160 kW Francis
Operation: 1957
T/G supplier: CKD, Skoda
Quick facts: The multipurpose Vir Dam on the Svratky River is one of the largest concrete structures in the county. The 75m high dam has a crest length of 390m. It is 50km from Brno and serves for flood control, hydropower and public water supply functions. The 10km long reservoir reaches 55m in depth and flooded several viallages. Prepearatory work bgan in 1947 and the project employed up to 1,400 workers who were housed nearby.

Photograph courtesy of E.ON Trend sro
Posted 14 Apr 2013

Vir-II
Location: Vysocina
Operator: E.ON Trend sro
Configuration: 1 X 890 kW Kaplan
Operation: 1957
T/G supplier: CKD, Vsetin
Quick facts: The Vir complex has this SHP running on a surge system at the main dam.

Photograph courtesy of E.ON Trend sro
Posted 14 Apr 2013

Vranov
Location: Jihomoravsky
Operator: E.ON Trend sro
Configuration: 3 X 6.3 MW Francis
Operation: 1934
T/G supplier: CKD, Skoda
Quick facts: The Vranov Dam is on the Dyji River. Construction got underway in Mar 1930 and took 3.5yrs. The poured concrecete gravity dam measures 54m high and has a 290m crest. The base is 27m wide, narrowing to 6m at the top. The right-side penstocks bring water to the dam toe powerhouse. The 2002 Czech floods were the worst in 500yrs at this location and caused damage at various points of the dam and assocated works. A visitor center was opened at Vranov in Jun 2011.

Photograph courtesy of E.ON Trend sro
Posted 14 Apr 2013

 
Vranov-3
Location: Jihomoravsky
Operator: E.ON Trend sro
Configuration: 2 X 22 kW semi-Kaplan
Operation: 2011
T/G supplier: ??
EPC: ELZACO spol sro
Quick facts: The Vranov-3 project was initiated after repairs at the Vranov complex dating to the 2002 flood. The ecological flow SHP is fully automatic.

Photograph courtesy of E.ON Trend sro
Posted 14 Apr 2013

Znojmo
Location: Jihomoravsky
Operator: E.ON Trend sro
Configuration: 2 X 890 kW Kaplan
Operation: 1966
T/G supplier: CKD
Quick facts: This SHP was built on the 20m tall, multipurpose Znojmo Dam on the Dyji River. The dam serves to re-regulate downstream flows below the Vranov Dam and its 5km reservoir reservoir supplies potable water for the area.

Photograph courtesy of E.ON Trend sro
Posted 14 Apr 2013