CCGT Plants in the USA - Southern California - A to L
Badger Creek
Location: CA
Operator: Delta Power LLC
Configuration: 46-MW LM5000 gas turbine CHP
Operation: 1991
Fuel: natural gas
T/G supplier: GE, Stewart & Stevenson, Brush
Quick facts: Steam is used by Occidental Petroleum for enhanced oil recovery.

Photograph courtesy of Delta Power LLC
Posted 20 Mar 2005

Bear Mountain
Location: CA
Operator: Delta Power LLC
Configuration: 46-MW LM5000 gas turbine CHP
Operation: 1995
Fuel: natural gas
T/G supplier: GE, Stewart & Stevenson, Brush
Quick facts: Steam is used by Texaco for enhanced oil recovery.

Photograph courtesy of Delta Power LLC
Posted 20 Mar 2005

Blythe
Location: CA
Operator: AltaGas
Configuration: 520-MW, 2+1 CCGT with V84.3A gas turbines
Operation: 2003
Fuel: natural gas
HRSG supplier: Vogt
T/G supplier: Siemens
EPC: Burns & Roe
Quick facts: Blythe is a zero discharge facility near the Arizona border. The plant was announced in Jun 2001 as a joint venture with Caithness Energy LLC, the original developer. Blythe operates on a merchant basis and delivers electricty to the grid via a 67mi transmission tie-line.The plant was acquired by AltaGas in 2014.

Photograph courtesy of Siemens
Posted 3 Feb 2008

Chalk Cliff
Location: CA
Operator: Delta Power LLC
Configuration: 46-MW LM5000 gas turbine CHP
Operation: 1990
Fuel: natural gas
T/G supplier: GE, Stewart & Stevenson, Brush
Quick facts: Steam is used by Berry Petroleum for enhanced oil recovery.

Photograph courtesy of Delta Power LLC
Posted 20 Mar 2005

Canyon
Location: CA
Operator: Anaheim Public Utilities
Configuration: 4 X 50-MW LM6000PC gas turbines
Operation: 2011
Fuel: natural gas
T/G supplier: GE
EPC: Burns & Row, Barton Malow
Quick facts: This GT plant completed in the fall of 2011. it is located in a tight urban setting and the facility, incluindg a 69kV switchyard, is enclosed with a 20ft masonry wall.

Photograph courtesy of Anaheim Public Utilities
Posted 21 Jan 2017

Carson Cogen
Location: CA
Operator: Energy Operations Group LLC
Configuration: 50-MW, 1+1 CCGT with LM6000 gas turbine
Operation: 1990
Fuel: natural gas
HRSG suppplier: B&W
T/G supplier: GE, Shin Nippon
EPC: Western Energy Engineers, B&W
Quick Facts:  This project in an industrial park in Carson supplies steam to Mountain Ice Water Co and sells electricity to SCE. The current owner is Carson Illinois Holding LLC, majoirty-funded by Crestwood Energy Investments, and fuel is supplied by JP Morgan Ventures Energy.

Photograph courtesy of Energy Operations Group LLC
Posted 23 Nov 2013

Chino Cogen
Location: CA
Operator: PIC Energy Services
Configuration: 27-MW, 1+1 CCGT with LM2500 gas turbine CHP
Operation: 1987
Fuel: natural gas
HRSG supplier: ??
T/G supplier: GE, Stewart & Stevenson, Brush, Shin Nippon
Quick facts: Steam is sold to the Chino Institute for Men and electricity to Southern California Edison.

Photograph courtesy of Delta Power LLC
Posted 20 Mar 2005

Colton
Location: CA
Operator: Colton Public Utilities
Configuration: 1 X 43 MW LM6000PC gas turbine
Operation: 2003
Fuel: natural gas
T/G supplier: GE
EPC: Noresco
Quick facts: Also known as Aqua Mansa. Project developed on a fast track with ground-breaking in Jan 2003 and commercial operating in Jun 2003. Noresco is the O&M contractor and also manages fuel procurement.

Photograph courtesy of City of Colton
Posted 17 Apr 2004

Corona
Location: CA
Operator: Consolidated Asset Management Services
Configuration: 1 X 47 MW LM5000PD gas turbine CHP
Operation: 1988
Fuel: natural gas
HRSG supplier: Deltak
T/G supplier: GE
EPC: PSE, Destec
Quick facts: This cogen plant is now owned by owned by WCAC Operating Co. It supplies electricity to Southern California Edison and thermal and electrical energy to Golden Cheese Co of California.

Photograph courtesy of Combined Cycle Journal
Posted 5 Aug 2015

CPV Sentinel
Location: CA
Operator: Competitive Power Ventures Inc
Configuration: 8 X 100 MW LMS100 gas turbines
Operation: 2012
Fuel: natural gas
T/G supplier: GE
EPC: Gemma Power Systems
Quick facts: CPV co-owns the $900mn SEP with GE Energy Financial Services (25%) and Diamond Generating Corp (50%). The project is near Desert Hot Springs and connects to the adjacent SCE Devers Substation. The plant went comercial on 16 May 2013, about 3mos early. In Aug 2013, SEP begins a long-term PPA with SCE.

Photograph courtesy of Competitive Power Ventures
Posted 27 May 2013

Cymric 36W
Location: CA
Operator: Chevron Corp
Configuration: 4 X 3.1-MW Centaur 40 gas turbines CHP
Operation: 1982
Fuel: natural gas
T/G supplier: Solar
Quick facts: Cymric in Kern Co was one of Central California's major oil fields and from 1909-200 produced about 350mn barrels of crude. It is still in production and this is one of numerous cogen plants in the area used for enhanced oil recovery.

Photograph courtesy of Precision Engine Controls Corp
Posted 21 Feb 2009

Double-C
Location: CA
Operator: Delta Power LLC
Configuration: 2 X 24-MW LM2500 gas turbines CHP
Operation: 1989
Fuel: natural gas
T/G supplier: GE, Stewart & Stevenson, Brush
Quick facts: Steam is used by Occidental Petroleum for enhanced oil recovery.

Photograph courtesy of Delta Power LLC
Posted 20 Mar 2005

El Segundo New
Location: CA
Operator: NRG Energy
Configuration: two 275-MW, 1+1 CCGT blocks with SGT6-5000F gas turbines
Operation: 2013
Fuel: natural gas
HRSG supplier: NEM
T/G supplier: Siemens
EPC: Siemens, ARB Inc
Quick facts: In Feb 2005, the CA Energy Commission issued a license for this air-cooled repowering project. The retired Units 1&2 were demolished in Feb 2011 and construction on the CCGT plant started in Jun 2013. Commercial operation was on 2 Aug 2013.

Photograph courtesy of NRG Energy
Posted 3 Aug 2013

Elk Hills
Location: CA
Operator: Sempra Energy Resources
Configuration: 500-MW, 2+1 CCGT with 7001FA gas turbines
Operation: 2003
Fuel: natural gas
HRSG supplier: IHI
T/G supplier: GE
EPC: Parsons
Quick facts: This plant is a joint venture of Sempra and Occidental Energy Ventures in the center of the 74mi² Elk Hills oil field operated by Occidental in western Kern County. The plant is connected to the grid by a new 9mi, 230kV line. Elk Hills cost $400mn and went commercial in Jul 2003.

Photograph courtesy of Ishikawajima-Harima Heavy Industries
Posted 17 Aug 2003

Glenarm GT & CC
Location: CA
Operator: Pasadena Water & Power
Configuration: 2 X 29-MW, GC4C1D gas turbines, 2 X 61-MW LM6000 gas turbines, one 71-MW, 1+1 CCGT block with LM6000 gas turbine
Operation: 1976-2016
Fuel: natural gas, oil
HRSG supplier: IST
T/G supplier: Curtis Wright, GE, Brush
EPC: GE, Sermatech, ARB Inc
Quick facts: The City of Pasadena’s power plant is located on a 14ac site in the southwestern portion of the city. The site consists of two groups of generating facilities bisected by the Los Angeles County Metropolitan Transportation Authority (Metro) Gold Line tracks: the Glenarm Plant to the west of the Gold Line and the Broadway Plant to the east. Glenarm GT 3&4 were ordered from GE on 11 Feb 2002. The CC project was approved in Jun 2014, ground-breaking was in Jul 2014, first fire was on 2 Apr 2016, and testing and commissioning began in May 2016. The new CC block went commercial on 19 Dec 2016. The block is said to have some of most stringent emission limits in the USA. The final project budget was $136.9mn.

Photograph courtesy of Pasadena Water & Power
Posted 24 Dec 2016

Goal Line
Location: CA
Operator: GE Energy
Configuration: 49.9-MW, 1+1 CCGT with LM6000 gas turbine CHP
Operation: 1994
Fuel: natural gas
HRSG supplier: Aalborg
T/G supplier: GE, Shin Nippon
EPC: Parsons Main, TIC
Quick facts: This cogeneration plant is owned by Goal Line LP. Steam is sold to the adjacent Iceoplex Escondido, a dual-sheet ice rink, and electricity is purchased by San Diego Gas & Electric.

Photograph courtesy of Goal Line LP
Posted 20 May 2009

Haynes Repower Phase I
Location: CA
Operator: Los Angeles Dept Water & Power
Configuration: 575-MW, 2+1 CCGT with 7001FA gas turbine
Operation: 2005
Fuel: natural gas
HRSG supplier: Alstom
T/G supplier: GE
EPC: Bibb, Kiewit
Quick facts: In Aug 2002, Kiewit Power Constructors was awarded a $235mn design-build contract for repowering Haynes 3&4. This involved retiring the old sets and building a completely new 2+1 block. Project quantities included 16,700yd³ of structural concrete, 725t of structural steel, 61,000ft of large bore pipe, 35,000ft of small bore pipe, 179,550ft of electrical conduit, 707,000ft of electrical wire and 46,800 electrical terminations. The project was completed one month ahead of schedule on 25 Jan 2005 and represents a 94% emissions reduction as compared to the original steam electric Units 3&4.

Photograph courtesy of Kiewit Corp
Posted 11 Apr 2009

Haynes Repower Phase II
Location: CA
Operator: Los Angeles Dept Water & Power
Configuration: 6 X 100 MW LMS 100 gas turbines
Operation: 2013
Fuel: natural gas
T/G supplier: GE
EPC: Kiewit
Quick facts: The Haynes GS second-phase repowering project will replace Units 5& 6 with six quick-start gas turbines. Ground-breaking was on 29 Sep 2011 and project hand-over is scheduled for May 2013.

Photograph courtesy of Los Angeles Dept of Water & Power
Posted 30 May 2011

High Desert
Location: CA
Operator: Tenaska Power Fund LP
Configuration: 750-MW, 3+1 CCGT with W501F gas turbine
Operation: 2003
Fuel: natural gas
HRSG supplier: Alstom
T/G supplier: SWPC, Toshiba
EPC: Bibb, Kiewit
Quick facts: Constellation Energy filed an Application for Certification for High Desert on 30 Jun 1997. This $350mn project was approved in May 2000 as one of the first major plants in Southern California in a decade. The site is the former George AFB in Victorville. Construction started 1 May 2001 and commercial operation was in Apr 2003. In Dec 2006, High Desert was one of six plants acquired by Tenaska from Constellation for $1.64bn.

Photograph courtesy of Constellation Energy
Posted 25 Sep 2003

High Sierra
Location: CA
Operator: Delta Power LLC
Configuration: 2 X 24-MW LM2500 gas turbines CHP
Operation: 1989
Fuel: natural gas
T/G supplier: GE, Stewart & Stevenson, Brush
Quick facts: Steam is used by Occidental Petroleum for enhanced oil recovery.

Photograph courtesy of Delta Power LLC
Posted 20 Mar 2005

Inland Empire
Location: CA
Operator: GE
Configuration: 2 X 405-MW single-shaft CCGT blocks with 7001H gas turbines
Operation: 2008
Fuel: natural gas
HRSG supplier: Deltak
T/G supplier: GE
EPC: Calpine
Quick facts: This was the launch project for the 60hZ 7H machine, designed for a thermal efficiency of 60%. The $500mn plant is owned by GE and its output and fuel supply will be managed by Calpine Energy Services. Shown is the erection of one of the HRSGs in Jun 2006.

Photograph courtesy of Bigge Crane and Rigging Co
Posted 30 May 2006

Indigo
Location: CA
Operator: Diamond Generating Corp
Configuration: 3 X 45-MW LM6000 gas turbines
Operation: 2001
Fuel: natural gas
T/G supplier: GE
EPC: R G Vanderweil Engineers, Gemma Power Systems
Quick facts: One of two fast-track peaking plants originally developed by InterGen in southern California and sold to Mitsubishi subsidiary Diamond Generating in Nov 2004. The plants sell 100% of their capacity and energy under tolling agreements with Shell affiliates, Coral Power LLC and Coral Energy Management LLC.

Photograph courtesy of Gemma Power Systems
Posted 15 Apr 2006

La Paloma
Location: CA
Operator: La Paloma Generating Co LLC
Configuration: Four 256-MW single-shaft CCGT blocks with GT24-ICS gas turbines
Operation: 2003
Fuel: natural gas
HRSG supplier: Alstom
T/G supplier: Alstom
EPC: Alstom, Jacobs Engineering Group
Quick facts: In Mar 2000, PG&E's National Energy Group started construction on La Paloma in McKittrick, about 110mi northwest of Los Angeles. At the time, this was California's largest greenfield merchant power project. The plant in was completed in Mar 2003 and four months later, NEG declared bankruptcy. In Aug 2005, Complete Energy Holdings LLC acquired the plant and in Apr 2010, the facility was acquired by Rockland Capital. On 6 Dec 2016, Rockland Capital affiliate La Paloma Generating Co filed for Chapter 11 bankruptcy. NAES is the plant operator.

Photograph courtesy of Alstom
Re-posted 22 May 2010

Larkspur
Location: CA
Operator: Diamond Generating Corp
Configuration: 2 X 45-MW LM6000 gas turbines
Operation: 2001
Fuel: natural gas
T/G supplier: GE
EPC: R G Vanderweil Engineers, Gemma Power Systems
Quick facts: One of two fast-track peaking plants originally developed by InterGen in southern California and sold to Mitsubishi subsidiary Diamond Generating in Nov 2004. The plants sell 100% of their capacity and energy under tolling agreements with Shell affiliates, Coral Power LLC and Coral Energy Management LLC.

Photograph courtesy of Gemma Power Systems
Posted 15 Apr 2006

Long Beach Rebuild
Location: CA
Operator: NRG Energy
Configuration: 4 X 65-MW GT11D5 gas turbines
Operation: 1995-2007
Fuel: natural gas
T/G supplier: BBC, Alstom
Quick facts: This site in the Port of Long Beach has been used for power generation for about 100yrs. These four machines started life in 1976 as BBC GT11D models. Three were upgraded to D5s in the mid 1990s when the plant was still owned by Southern California Edison Co. The plant was mothballed in 2005, but four gas turbines were restarted in 2007 as fast-start peakers for a 10yr SCE contract. The fourth unit was upgraded to D5 in 2007.

Photograph courtesy of Combined Cycle Journal
Posted 30 Apr 2008

Abbreviations

Data: industcards, Platts UDI World Electric Power Plants Data Base

Updated 21-Jan-2017