CCGT Plants in the USA - Northern California
Almond-2
Location: CA
Operator: Turlock Irrigation District
Configuration: 3 X 58-MW LM6000PG gas turbines
Operation: 2012
Fuel: natural gas
T/G supplier: GE
EPC: Performance Mechanical Inc
Quick facts: This $200mn project opened on 18 Jul 2012.

Photograph courtesy of Combined Cycle Journal
Re-posted 5 Aug 2015

Cardinal Cogen
Location: CA
Operator: Stanford University
Configuration: 49-MW, 1+1 CCGT with 6001B gas turbine CHP
Operation: 1987 (ret)
Fuel: natural gas
HRSG supplier: Vogt
T/G supplier: GE, ABB
EPC: Brown & Root, GE
Quick facts: When commissioned, this PURPA plant was owned and operated by Cardinal Cogen, a subsidiary of General Electric. Stanford used about 60% of the electrical power with the balance sold to PG&E and 80% of the low-grade waste heat. This was distributed as low-pressure steam to campus and hospital buildings for comfort and domestic water heating, and to Stanford's Chilled Water Plant for steam powered chillers. The plant was closed 1 Apr 2015 and sold to Stanford for $1.

Photograph courtesy of Stanford University
Posted 15 Apr 2015

Colusa
Location: CA
Operator: Pacific Gas and Electric Co
Configuration: 657-MW, 2+1 CCGT with 7001FA gas turbines
Operation: 2010
Fuel: natural gas
HRSG supplier: Nooter
T/G supplier: GE
EPC: WorleyParsons, Gemma
Quick Facts: Colusa broke ground on 19 Nov 2008 went commercial on 22 Dec 2010. The 100ac site is near the town of Maxwell, about 75mi northwest of Sacramento. Nearby are a 230kV transmission line and natural gas pipeline. The project cost about $673mn

Photograph courtesy of Gemma
Posted 3 Aug 2013

Cosumnes
Location: CA
Operator: Sacramento Municipal Power Authority
Configuration: 500-MW, 2+1 combined-cycle CHP plant with 7001FA gas turbines
Operation: 2006
Fuel: natural gas
HRSG supplier: Nooter
T/G supplier: GE, MHI
EPC: Utility Engineering, Frucon
Quick facts: This plant is located half a mile south of the closed Rancho Seco nuclear plant and was sited there to use existing transmission and water delivery facilities. A 26mi extension to an existing gas pipeline was built for the new plant.

Photograph courtesy of Sacramento Municipal Utility Dist
Re-posted 26 May 2007

Crockett
Location: CA
Operator: Quixx Corp
Configuration: 240-MW single-shaft combined-cycle CHP plant with 7001FA gas turbine
Operation: 1996
Fuel: natural gas
HRSG supplier: Vogt
T/G supplier: GE
EPC: Bechtel
Quick facts: About 260,000 lbs/hr of steam is sold to C&H Sugar and electricity on a fully dispatchable basis to Pacific Gas and Electric. Crockett has a Marley air-cooled system with ultra low-noise fans.

Photograph courtesy of Delta Power LLC
Posted 20 Mar 2005

Donald Von Raesfeld
Location: CA
Operator: Silicon Valley Power
Configuration: 154-MW, 2+1 combined-cycle CHP plant with LM6000 Sprint gas turbines
Operation: 2005
Fuel: natural gas
HRSG supplier: ATS
T/G supplier: GE, MHI
EPC: Black & Veatch
Quick facts: The plant is on a compact 1.68ac site and provides essential power service to a number of nearby web server centers.

Photograph courtesy of Bay Solutions Corp
Posted 26 Mar 2005

Gateway
Location: CA
Operator: Pacific Gas and Electric Co
Configuration: 566-MW, 2+1 CCGT with 7001FA+e gas turbines
Operation: 2009
Fuel: natural gas
HRSG supplier: Vogt
T/G supplier: GE
EPC: B&V, Granite, Kiewit
Quick facts: On 31 Jan 2000, Southern Energy filed an Application for Certification (AFC) for Gateway Contra Costa Power Unit 8 located within the existing Gateway Contra Costa Power Plant site complex in Contra Costa County, just north of the City of Antioch. Construction started in early 2001. As part of a 2005 settlement with Mirant Services LLC, PG&E took ownership of the project and re-started construction in Jan 2007. COD was on 4 Jan 2009.

Photograph courtesy of Combined Cycle Journal
Posted 28 Apr 2012

Hanford Peaker
Location: CA
Operator: AltaGas
Configuration: 2 X 48.5-MW LM6000 gas turbines
Operation: 2001
Fuel: natural gas
T/G supplier: GE
EPC: B&V, Frucon
Quick facts: This project is in the San Joaquin Valley and it went commercial on 21 Sep 2001. It is one of three gas-fired plants bought by AltaGas in Sep 2015. Hanford has a PPA with PG&E expiring in 2022.

Photograph courtesy of AltaGas
Posted 19 Jan 2017

Henrietta Peaker
Location: CA
Operator: AltaGas
Configuration: 2 X 48-MW LM6000 gas turbines
Operation: 2001
Fuel: natural gas
T/G supplier: GE
EPC: B&V, Frucon
Quick facts: This project is in Lemoor and went online on 1 Jul 2002. It is one of three gas-fired plants bought by AltaGas in Sep 2015. Henrietta has a PPA with PG&E expiring in 2022.

Photograph courtesy of AltaGas
Posted 19 Jan 2017

King CIty
Location: CA
Operator: Calpine Corp
Configuration: 162-MW, 1+1 CCGT with 7001EA gas turbines CHP, 1 X 42-MW LM600PC-S gas turbine
Operation: 1989-2002
Fuel: natural gas
HRSG supplier: Nooter
T/G supplier: GE, Stal, Brush
EPC: Bechtel, Calpine
Quick facts: Electricity generated by the King City Cogeneration Plant is sold to PG&E and steam is sold to Mesa Business Park under a long-term contract. The King CIty peaker was added to serve a 10yr contract with DWR.

Photograph courtesy of GE Energy Financial Services
Posted 30 Aug 2014

Lodi Energy Center
Location: CA
Operator: Northern California Power Agency
Configuration: 255-MW single-shaft CCGT with SGT6-5000F gas turbine
Operation: 2012
Fuel: natural gas
HRSG supplier: Nooter
T/G supplier: Siemens
EPC: ARB, WorleyParsons, Cupertino Electric
Quick facts: The $388mn LEC project was completed in Aug 2012 a few months past schedule. NCPA purchases wastewater from the the White Slough Water Pollution Control Facility for cooling makeup and other onsite water usage. Ten of NCPA’s 17 members, as well as four other public power companies financed the project.

Photograph by Keri Brenner (HealdsburgPatch.com)
Re-posted 8 Aug 2012

Los Medanos
Location: CA
Operator: Calpine Corp
Configuration: 566-MW, 2+1 CCGT with 7001FA+e gas turbine CHP
Operation: 2001
Fuel: natural gas
HRSG supplier: Nooter
T/G supplier: GE
EPC: Bibb, Kiewit
Quick facts: Los Medanos supplies electricity and steam to the USS Posco works.

Photograph courtesy of Calpine
Posted 15 Aug 2004

Marsh Landing
Location: CA
Operator: NRG Energy
Configuration: 4 X 190-MW SGT5-5000F gas turbines
Operation: 2013
Fuel: natural gas, oil
T/G supplier: Siemens
EPC: Kiewit
Quick facts: This project has a 27ac plot at the Contra Costa PS site near Antioch, 45km east-northeast of San Francisco. Marsh Landing went commercial on 1 May 2013, Contra Costa Units 6&7 having closed the day before. PG&E has a 10yr PPA for the entire plant output. PG&E also owns operates the Gateway PS at the other end of the property.

Photograph courtesy of NRG Energy
Posted 25 May 2013

McClellan
Location: CA
Operator: Sacramento Municipal Utility Dist
Configuration: 1 X 72 MW 7001 gas turbine
Operation: 1986
Fuel: natural gas
T/G supplier: John Brown, Brush

Photograph courtesy of Sacramento Municipal Utility Dist
Posted 7 Sep 2003

Metcalf Energy
Location: CA
Operator: Calpine Corp
Configuration: 600-MW, 2+1 combined-cycle CHP plant with W501FD gas turbines
Operation: 2005
Fuel: natural gas
HRSG supplier: Nooter
T/G supplier: SWPC
EPC: Calpine
Quick facts: After a lengthy and contentious development process, Metcalf became the first large power station in Silicon Valley. The project includes a new 230kV substation and a short transmission line connecting the Pacific Gas and Electric grid. A specially-designed exterior facade and other architectural treatments were included to reduce the facility's visual impact.

Photograph courtesy of Combined Cycle Journal
Posted 14 Feb 2006

NCPA Project 1
Location: CA
Operator: Northern California Power Agency
Configuration: 5 X 25 MW 5000PPPP gas turbines
Operation: 1986
Fuel: natural gas, oil
T/G supplier: Nuovo Pignone, Ansaldo
EPC: Ebasco
Quick facts: NCPA Project 1 comprises five dual fuel GTs in the cities of Alameda, Roseville, and Lodi. Each unit can be operated separately and started remotely from NCPA Central Dispatch in Roseville. Members participating in Project 1 are the cities of Alameda, Healdsburg, Lodi, Lompoc, Roseville, Santa Clara, Ukiah, and the Plumas Sierra Electric Cooperative.

Photograph courtesy of Northern California Power Agency
Posted 7 May 2006

Oakland
Location: CA
Operator: Duke Energy North America
Configuration: 3 X 55 MW FT4C gas turbines
Operation: 1978
Fuel: kerosene
T/G supplier: PW
Quick facts: Oakland was acquired from Pacific Gas and Electric in July 1998 and is now run as a merchant plant.

Photograph courtesy of Duke Energy
Posted 26 Jan 2005

Oakland WWTP
Location: CA
Operator: East Bay Municipal Utility District
Configuration: 1 X 4.6-MW Mercury 50 gas turbine CHP
Operation: 2008
Fuel: digester gas
T/G supplier: Solar
Quick facts: This new GT was dedicated on 4 Apr 2012. The $19mn installation uses digester gas from 75mn gpd of wastewater plus truckloads of other organic waste materials including restaurant grease, cheese and poultry wastes, and winery wastewater. The GT was added to a set of three 2.15-MW Enterprise gas gensets (online in 191, to the right in the photo) which should enable the WTP to become the first in the nation to produce enough energy from organic waste to export to the grid. After the digestion process is complete, remaining biosolds are used as a soil amendment for non-food crops or landfilled.

Photograph courtesy of East Bay Municipal Utility District
Posted 28 Apr 2012

Panoche
Location: CA
Operator: Energy Investors Funds LLC
Configuration: 4 X 100-MW LMS100
Operation: 2009
Fuel: natural gas
T/G supplier: GE
EPC: Kiewit
Quick facts: This plant in Firebaugh, western Fresno Co, has a 20yr PPA from Pacific Gas and Electric Co awarded in Apr 2006 per the utility's long-term resource plan issued in Jul 2004. DG Power acted as original developer and continued to work with Energy Investors, which acquired the project in 2006. Kiewit was awarded the EPC contract in Jul 2007 and construction started in Feb 2008 following CEC final approval in Dec 2007. The plant was built with $330mn of debt financing. These are the first LMS100 machines in California. Panoche was named a Power magazine Top Plant in 2010

Photograph courtesy of Power
Re-posted 11 Sep 2010

Pixley
Location: CA
Operator: Pixley CoGen Partners
Configuration: 1 X 6-MW CHP
Operation: 2008
Fuel: natural gas
T/G supplier: Solar
Quick facts: This small power plant supplies electricity and up to 130,000pph of steam to Calgren Renewable Fuels and Pixley Ethanol LLC. Sierra Energy Co is a co-owner of the project.

Photograph courtesy of Pixley CoGen Partners
Posted 1 Jul 2009

Ripon Modesto
Location: CA
Operator: Modesto Irrigation District
Configuration: 2 X 50-MW LM6000 Sprint gas turbines
Operation: 2006
Fuel: natural gas
T/G supplier: GE
EPC: IEC Corp
Quick facts: These units were packaged by Kvaerner in Norway and acquired pre-owned but unused. The machines put out about 37 MW without Sprint boosting and inlet air chilling. The plant has a simple-cycle catalyst system from Express Integrated Technologies. It went online in Apr 2006.

Photograph courtesy of IEC Corp
Posted 21 Jan 2017

Roseville Energy
Location: CA
Operator: Roseville Electric Dept
Configuration: 160-MW, 2+1 CCGT with SGT-800 gas turbines
Operation: 2007
Fuel: natural gas
HRSG supplier: Vogt
T/G supplier: Siemens
EPC: WorleyParsons, Gemma
Quick Facts: Roseville Energy's development began in 2002 and Calpine and CH2M-Hill were retained as consulting engineers in spring 2003. A CEC Applcation for Certification was filed in Oct 2003, construction began in Aug 2005, and substantial completion was achieved in Oct 2007. The Roseville project is adjacent to Pleasant Grove Wastewater Treatment Plant, which supplies makeup water, and the power project scope included a zero liquid discharge system from Aquatech International.

Photograph courtesy of Combined Cycle Journal
Posted 5 Jul 2008

Sacramento Campbell Soup
Location: CA
Operator: Sacramento Power Authority
Configuration: 172-MW, 1+1 CCGT with V84.2 gas turbine CHP
Operation: 1997
Fuel: natural gas
HRSG supplier: Nooter
T/G supplier: Siemens
EPC: CNF, Parsons

Photograph courtesy of Sacramento Municipal Utility Dist
Posted 17 Aug 2003

Sacramento Carson
Location: CA
Operator: Carson Energy Corp
Configuration: 55-MW, 1+1 CCGT with LM6000 gas turbine CHP, plus 1 X 35 MW LM6000
Operation: 1995
Fuel: natural gas
HRSG supplier: Deltak
T/G supplier: GE, ABB
EPC: CCF, Parsons

Photograph courtesy of Sacramento Municipal Utility Dist
Posted 17 Aug 2003

Sacramento SCA
Location: CA
Operator: Sacramento Power Authority
Configuration: 127-MW, 2+1 CCGT with LM6000 gas turbine CHP
Operation: 1997
Fuel: natural gas
HRSG supplier: Nooter
T/G supplier: GE
EPC: Black & Veatch, Walsh

Photograph courtesy of Sacramento Municipal Utility Dist
Posted 7 Sep 2003

Tracy
Location: CA
Operator: AltaGas
Configuration: 330-MW, 2+1 CCGT with 7001EA gas turbines
Operation: 2003-2012
Fuel: natural gas
HRSG supplier: Alstom
T/G supplier: GE, Alstom
EPC: B&V, Wood Group
Quick facts: This project is in the San Joaquin Valley about 60mi east of San Franciso. It was developed and built by GWF Energy as a peakding plant beginning in 2001 and converted to an air-cooled CCGT plan in 2012. This is one of three gas-fired plants bought by AltaGas in Sep 2015. Tracy is grid-connected through a 115kV PG&E switchyard and has a tolling PPA with PG&E expiring in 2022.

Photograph courtesy of AltaGas
Posted 19 Jan 2017

Walnut Energy
Location: CA
Operator: Turlock Irrigation District
Configuration: 258-MW, 2+1 CCGT with 7001EA gas turbines
Operation: 2006
Fuel: natural gas
HRSG supplier: Nooter
T/G supplier: GE, Siemens
EPC: UTEC, Calpine
Quick facts: In 2003, Turlock Irrigation District and the Merced Irrigation District formed the Walnut Energy Center Authority to finance, construct, and operate this combined-cycle plant. In April 2004, the WECA issued $201mn in tax-exempt and taxable revenue bonds to finance construction. The plant uses treated effluent from the city's wastewater treatment plant for cooling and process water. The gas turbines have dry low-NOX combustors and the HRSGs use SCR for NOX control.

Photograph courtesy of Turlock Irrigation District
Posted 4 Mar 2006

Abbreviations

Data: industcards, Platts UDI World Electric Power Plants Data Base

Updated 21-Jan-2017