CCGT Plants in Spain - Other Regions
Arrubal
Location: La Rioja
Operator: Gas Natural SDG SA
Configuration: 2 X 400 MW single-shaft CCGT blocks with V94.3A gas turbines
Fuel: natural gas, gasoil
Operation: 2004
HRSG supplier: Nooter
T/G supplier: Siemens
EPC: Siemens
Quick facts: The project was approved in May 2003 and cost about €370mn.

Photograph courtesy of Gas Natural SDG SA
Posted 9 Nov 2005

Barranco de Tirajana
Location: Islas Canarias
Operator: Endesa
Configuration: 2 X 210 MW, 2+1 CCGT blocks with 6001FA gas turbines
Fuel: diesel oil
Operation: 2003-2007
HRSG supplier: Babock Borsig Power
T/G supplier: GE, Siemens
EPC: Duro Felguera

Photograph courtesy of Hitachi Europe
Posted 9 Mar 2007

Cas Tresorer
Location: Islas Baleares
Operator: Gesa-Endesa
Configuration: 2 x 230 MW, 2+1 CCGT blocks with 6001FA gas turbines
Fuel: natural gas, diesel oil
Operation: 2006-2010
HRSG supplier: NEM
T/G supplier: GE
EPC: Duro Felguera
Quick facts: This plant is in Palma de Mallorca. Phase-I cost €200mn. A new 220/66kW substation was built at the site. Conversion to natural gas completed Dec 2011 following 2009 operation of the 267km, Enagas Balearic gas pipeline.

Photograph courtesy of Duro Felguera SA
Posted 27 Feb 2011

Castejon-I
Location: Navarra
Operator: HC Energia
Configuration: 400-MW single-shaft CCGT with GT26B gas turbine
Fuel: natural gas
Operation: 2003
HRSG supplier: CMI
T/G supplier: Alstom
EPC: Alstom, Duro Felguera

Photograph courtesy of Alstom Power
Posted 20 Mar 2004

Castejon-II
Location: Navarra
Operator: HC Energia
Configuration: 424-MW single-shaft CCGT with GT26B gas turbine
Fuel: natural gas
Operation: 2008
HRSG supplier: CMI
T/G supplier: Alstom
EPC: Alstom, Duro Felguera

Photograph courtesy of Duro Felguera SA
Posted 27 Feb 2011

Castelnou
Location: Teruel
Operator: GDF SUEZ Energia Iberia
Configuration: 800-MW, 2+1 CCGT with M701F3 gas turbines
Fuel: natural gas
Operation: 2006
HRSG supplier: CMI
T/G supplier: MHI, Melco
EPC: Incitec, Dragados
Quick facts: Construction started on 27 Oct 2003 and commercial operations began on 5 Jul 2006. The plant cost €320mn.

Photograph courtesy of GDF SUEZ
Re-posted 29 Feb 2012

Enercrisa
Location: Burgos
Operator: Enercrisa (Iberdrola)
Configuration: 1 x 15 MW MF111B gas turbine CHP
Fuel: natural gas
Operation: 1994
T/G supplier: MHI, Tuma
Quick facts: This installation supplies power and steam to the world's largest glauberite mine (sodium calcium sulfate), a mineral used in dying, solar cells, and medicine.

Photograph courtesy of Grupo Crimidesa
Posted 6 Aug 2005

Escatrón
Location: Zaragoza
Operator: E.ON Espana
Configuration: 70-MW, 2+1 CCGT with V94.3A4 gas turbines
Fuel: natural gas, diesel oil
Operation: 2008
HRSG supplier: Ansaldo
T/G supplier: Ansaldo
EPC: Ansaldo, Carbonell Figueras, Demont srl
Quick facts: In Nov 2004, E.ON's 770-MW CCGT at Escatron was granted environmental approval by the Aragon authorities and the Secretaria de Energia signed off in Feb 2005. The €400mn project was built at the site of an existing 80-MW coal-fired plant and connects to the grid though an existing 400kV substation. Ansaldo was awarded the EPC contract in Jul 2005.

Photograph courtesy of E.ON
Posted 14 Aug 2013

Escatrón Combi
Location: Zaragoza
Operator: Global 3 Energia SPCA
Configuration: 276-MW, 4+1 CCGT with LM6000P gas turbines
Fuel: natural gas
Operation: 2007-2010
HRSG supplier: Innovative
T/G supplier: GE, Siemens
EPC: GE, Heymo Ingeniería, Tecnicas Reunidas
Quick facts: This site comprises 40ac near the Ebro River. The plant cost about €300mn and was delayed approximately two years. Development started in Nov 2003.

Photograph courtesy of Global 3 Energia SPCA
Posted 10 Sep 2008

Granadilla
Location: Islas Canarias
Operator: Endesa Unelco
Configuration: 210-MW, 2+1 CCGT with 6001FA gas turbines
Fuel: oil
Operation: 2003-2005
HRSG supplier: NEM
T/G supplier: GE
EPC: Tecnicas Reuindas, Empresarios Agrupados
Quick facts: This plant was ordered in Apr 2003. The gas turbines were sourced from Belfort, France, and the steam set from Schenectady, NY.

Photograph courtesy of Endesa
Posted 26 Mar 2006

Las Salinas
Location: Las Palmas
Operator: Unelco-Endesa
Configuration: 150-MW, gas turbines and IC engines
Fuel: diesel oil, LFO
Operation: 1975-2003
T/G supplier: ABB, Sulzer, MAN B&W
EPC: Tecnicas Reuindas, Empresarios Agrupados
Quick facts: Ths plant covers electricity supply for Isla Fuerteventura.

Photograph courtesy of Endesa
Posted 1 Jan 2013

Puentes
Location: A Coruna
Operator: Endesa
Configuration: 800-MW, 2+1 CCGT with 9001FB gas turbines
Fuel: natural gas
Operation: 2008
HRSG supplier: Deltak
T/G supplier: GE
EPC: GE, Duro Felguera
Quick facts: At the As Pontes site.

Photograph courtesy of Duro Felguera SA
Posted 27 Feb 2011

This was photograph number 6,000 posted in the Power Plants Around the World gallery.

 

Sabon CCGT
Location: A Coruna
Operator: Gas Natural Fenosa
Configuration: 400-MW, single-shaft CCGT with 9001FA gas turbine
Fuel: natural gas
Operation: 2008
HRSG supplier: Doosan
T/G supplier: GE
EPC: Cobra
Quick facts: In May 2004, CNE approved Union Fenosa's application for the addition of two 400-MW CCGT blocks to the 470-MW Sabon power station near La Coruna. Originally, both blocks were scheduled for 2006, but the first actually went online in 2008 and the second block was deferred. Gas is supplied from the Reganosa LNG terminal in nearby Mugardos.

Photograph courtesy of Gas Natural Fenosa
Posted 19 Feb 2012

Son Reus
Location: Islas Baleares
Operator: Gesa-Endesa
Configuration: 1 x 150 MW, 2+1 CCGT with 6001B gas turbines, 1 X 210 MW, 2+1 CCGT block with 6001FA gas turbines
natural gas, Fuel: diesel oil
Operation: 2000-2005
HRSG supplier: CMI, NEM
T/G supplier: Alstom, GE, Siemens
EPC: Alstom, Idom, Duro Felguera
Quick facts: Conversion to natural gas completed Dec 2011 following 2009 operation of the 267km, Enagas Balearic gas pipeline.

Photograph courtesy of Hitachi Europe
Posted 9 Mar 2007