CCGT Plants in Ecuador
Enrique Garcia
Location: Guayas
Operator: CELEC Electroguayas
Configuration: 1 X 102 MW W501D5 gas turbine
Fuel: diesel oil, natural gas
Operation: 1997
T/G supplier: WH
EPC: Schrader Camargo

Photograph courtesy of Electroguayas SA
Posted 30 Jul 2006

Machala-II
Location: Cotopaxi
Operator: CELEC-Termogas Machala
Configuration: 2 X 62 MW 6001FA gas turbines
Fuel: natural gas
Operation: 2002
T/G supplier: GE
EPC: Washington Group International, Santos CMI, Cointec
Quick facts: This gas-by-wire plant near Guayaquil iwas developed by Noble Energy and fueled by gas from the Amistad offshore gas field.. The 14.5ha site is in Baja Alto, about 2km from the coast, and is connected to the gas production works by a 70km pipeline. A 14km transmission line connects to Transelectricís 138kV line Milagro-Machala. The gas turbines were ordered in Jun 2000. In May 2011, the project reverted to the government.

Photograph courtesy of Washington Group International
Posted 30 Jun 2007

Manta Miraflores
Location: Miraflores
Operator: CELEC Termopichincha
Configuration: 1 X 22.8 TM-2500 gas turbine
Fuel: diesel oil
Operation: 2009
T/G supplier: GE
EPC: SANTOS CMI
Quick facts: This was part of an emergency generation project. The gas turbine was flown to Ecuador from Houston via Antonov AN 124 in Dec 2009 and installed immediately in Manta.

Photograph courtesy of Corp Electrica del Ecuador EP
Posted 5 Feb 2011

 
Pascuales-II
Location: Guayas
Operator: CELEC Termopichincha
Configuration: 6 X 22.8 TM-2500 gas turbine
Fuel: diesel oil
Operation: 2010
T/G supplier: GE
EPC: SANTOS CMI
Quick facts: This project comprised the balance of a CELEC order to GE for seven gas turbines for emergency generation. All machines were installed and operating with 2mos. The Pascuales-II project cost about $190mn, of which $117mn was for the equipment

Photograph courtesy of Presidencia de la Republica del Ecuador
Posted 5 Feb 2011

  Santa Rosa
Location: Pichincha
Operator: CELEC Termopichincha
Configuration: 3 X 17 5001PTG gas turbines
Fuel: diesel oil
Operation: 1981
T/G supplier: AEG
Quick facts: Santa Rosa went commercial in Mar 1981. The site is in Cutuglahua outside Quitro. Two machines act as synchronous generators delivering reactive power to the SNI.

Photograph courtesy of Corp Electrica del Ecuador EP
Posted 6 Feb 2011

Abbreviations

Data: industcards, Platts UDI World Electric Power Plants Data Base

Updated 22-Jul-2015